Project name: Changzhou Economic Development Zone 1.5MW BIPV roof
Project address: Zhongwu Avenue, Changzhou Economic Development Zone
Project area: about 8,000 square meters
Project installed capacity: 1.5MW
Project completion time: September 2022
Project design plan: The design of directly changing the flat cement roof of the workshop to a slope, and the roof of the R&D building is to erect a layer of steel structure, and directly lay the Jiangsu Coop&Inno BIPV photovoltaic system on the steel structure. The bottom owner will use it as a training and expansion training room.
Project design advantages: protect the cement roof, waterproof and heat insulation, one more layer of space can be used for other purposes.